06/10/2020 | ENCROACHMENT | DEVELYN SPEKNER | COMPLETED | precon pics | |
|
06/17/2020 | ENCROACHMENT | DEVELYN SPEKNER | APPROVED | Excav for vault, sidewalk demo | 6/18/2020 11:19:01 AM
Underground Electric contractor for PGE prepping site. Plates and cutback over demo sidewalk and vault loc. Vault to be delivered Monday. Finding conduits in lawns of 366 and 356 Glenbrook tomorrow. PGE crews also onsite beginning electrical line installation in existing vaults and boxes.
|
|
06/18/2020 | ENCROACHMENT | DEVELYN SPEKNER | PARTIAL APPROVAL | excavation for conduit | 6/18/2020 3:02:12 PM
Underground electric continues work at 366 and 356 Glenbrook for the PGE conduit in the joint trench in their front yards. PGE crews continue to pull wires through their existing vaults. Contractor will be back Monday to continue excavation for conduit.
|
|
06/23/2020 | ENCROACHMENT | DEVELYN SPEKNER | PARTIAL APPROVAL | sand slurry at excavation | 6/23/2020 2:56:55 PM
Contractor completed conduit installation from vault to private property and nearly to joint trench. More excavation at 366 Glenbrook needed to bring conduit to joint trench with ditch witch. Contractor said should be back tomorrow to finish all excavation work and be ready for PGE crews Thurs to do splicing and pulling. PGE onsite today doing pulling in other vaults in preparation for the vault in street to be completed.
|
|
06/24/2020 | ENCROACHMENT | DEVELYN SPEKNER | PARTIAL APPROVAL | conduit install continues | |
|
06/26/2020 | ENCROACHMENT | | APPROVED | concrete sidewalk rebar and install | 6/26/2020 3:50:35 PM
Contractor said they completed conduit connections to PGE conduit and backfilled last night at 5pm with sand. All lawn potholes were backfilled with sand to be restored with top soil and sod later. Sidewalk rock, rebar and concrete installed per plan. Will need to check backfill against walkway completed when forms removed.
|
|
06/29/2020 | ENCROACHMENT | DEVELYN SPEKNER | APPROVED | pavement restoration | 6/29/2020 5:22:37 PM
Contractor not prepared with a paving machine. Grinder was a smaller rolling unit with teeth that gives a more uneven surface. Grind area met requirements. Contractor had to lay all asphalt by hand with compaction roller and excavator. Whacker and Powderpuff also on site to help compact small areas. Pavement fabric used was Trupave brand. Tack oil was spread by hand sprinkling with a brush over surface and brush application on pavement side edges. He said it will be two separate asphalt loads to complete. An eight man crew with one designated as flagged.
|
|
06/30/2020 | ENCROACHMENT | DEVELYN SPEKNER | PARTIAL APPROVAL | sprinklers restored | 6/30/2020 3:53:38 PM
turf still remained undone when I left jobsite about 2:30 pm. Sprinklers were restored at 366 Glenbrook as working better than before. Some sprinkler heads were damaged previously and work less effectively, but were not damaged by this work so we left them as is. Sprinklers at 356 Glenbrook were not functioning before work was done. Any new damage to sprinkler lines was repaired; old uncapped lines previously broken prior to arriving onsite were just capped in place to prevent water damage if valves were turned on at the house. Homeowners were aware of damage to lines because they water their lawn with a hose and spraying sprinkler. Turf was not yet restored when I left. Crew was pulling rope through new and existing PGE conduits for their future work.
|
|
07/01/2020 | ENCROACHMENT | DEVELYN SPEKNER | APPROVED | Turf restored with soil and seed | 7/1/2020 8:17:48 AM
Contractor completed turf restoration at 356 and 366 Glenbrook see photos. Keep permit open until PGE completes their work in the vault and completes the loop to other vaults and locations.
|
|
08/21/2020 | ENCROACHMENT | DEVELYN SPEKNER | APPROVED | all work completed | |
|